Wednesday, March 23, 2016

Tree project update

All but 5 of the 120+ stumps have been ground and cleaned up. About 80% of the stump holes have been filled. So far we have used over 80 tons of topsoil. Some areas have been seeded, but most still need a finish grade and soil prep. I couldn't be happier with where we are at on this project and with the dry weather the past 7 days, we are definitely ahead of schedule.
Stumps on #12 Devlin Tee ground, before they were cleaned up

Stump shavings cleaned up and holes filled - Still need finish grade and seed

We are trying different ways to level areas....this has been the best so far with a tiller attachment for the tractor.  This helps level everything out.  This area was raked and seeded later today.

Trenching an area where a stump was on 2/3 Devlin

After french drain was installed, finish work with topsoil was done