The Devlin bunker project started a week ago. So far they have shelled out all the old sand on holes 1 thru 6, 9, 17 and 18. They are putting the new drainage tile in and getting ready for all the gravel. They are making very good time so far. Below are some pictures.
|
#1 bunker being shelled out |
|
#2 Bunker reshaped from the backside |
|
#2 back side had no lip and balls rolled out of the bunker. Around 500 square foot was removed and a new higher lip was added. |
|
Final shape of the bunker after the small left sand finger was removed. |
No comments:
Post a Comment